Cast In Situ / Çandybil Bridge / Turkmenistan

ÇANDYBIL BRIDGE / CAST-IN-SITU / PT / TURKMENISTAN

Description of the Work:
• There are 4 cast in situ post-tensioned concrete slab bridges. Trompet Bridge is composed of 2 identical parallel decks. • Each deck is composed of 2 spans: 34 m+34 m. Total deck length is 136 m. • Bekrowa Yonca Bridge is composed of 4 identical parallel decks. Each deck is composed of 2 spans: 30 m+30 m. Total deck length is 240 m. • Çandybil Bridge is composed of 4 identical paralel decks. Each deck is composed of 6 spans: 23 m+4x27 m+23 m. Total deck length is 308 m. • Bekrowa Bridge is composed of 2 identical paralel decks. Each deck has one span, 35 m. Total deck length is 70 m.

Freysaş Mission:
Freysaş was in charge of supply and installation of PT, expansion joints and seismic bearings:
• 469 tons of PT
• 364 m WD 230 Expansion Joint
• 76 units Pot Bearings